Case details
Read the grounds of judgmentThe issue
The Defendant, as employer, appointed the Plaintiff as main contractor for a mixed development in Penang under the PAM Contract 2006 for RM109,038,317.07. Years after practical completion, and at the Plaintiff's request, the Defendant's architect reassessed extension of time and moved the completion date from 14.10.2015 to 17.12.2015. The Defendant rejected the reassessment. On the Defendant's case the delay was 69 days (liquidated and ascertained damages of RM4,692,000.00); on the Plaintiff's case it was 5 days. [5], [10]-[16]
The Plaintiff commenced arbitration to recover the liquidated damages withheld. Relying on Clause 34.8(d) and (e) of the PAM Contract, the Defendant asked the Arbitrator to open up, review and revise its own architect's reassessment. The Arbitrator did so, restored the earlier completion date and largely upheld the Defendant's deduction. [17], [21], [23], [24]
The Plaintiff applied to set aside the Final Award under Sections 37(1)(a)(v) and 37(1)(b)(ii) read with 37(2)(b)(ii) of the Arbitration Act 2005, contending that the Arbitrator had decided what was in truth a dispute between the Defendant and its own architect, and that the rules of natural justice were breached because the architect was not heard. [3], [29]
The decision
- Setting aside refused. The Court dismissed the application with costs of RM15,000.00. The dispute referred was one between the Plaintiff and the Defendant as to extension of time and liquidated damages, and the correctness of the reassessment was the very difference which the claim generated and the defence answered.
MBSB cannot found its claim on the reassessment and at the same time say that its correctness lay outside the reference.
[49], [54], [154] - Reviewing a certificate is not a claim against the certifier. No relief was sought against, and the award did not bind, the architect or the engineer.
reviewing a certificate issued by a party’s own agent, as an incident of resolving the dispute between the arbitrating parties, is a wholly different exercise from adjudicating a freestanding claim against that agent.
[55], [56] - Agency does not make the certificate conclusive. When certifying, the architect must act fairly and independently as between both parties. Section 179 of the Contracts Act 1950 does not make a reviewable certificate conclusive against the employer merely because the employer engaged the certifier.
Opening up a certificate is concerned with the parties’ true contractual entitlement, not fault.
[58]-[60], [70] - The arbitration was the right forum. The Plaintiff's proposed course would have led to a multiplicity of proceedings, with its true entitlement litigated outside the forum the parties had chosen.
A separate action against the Architect could never determine, as against MBSB, the EOT due or the LAD SPSB might retain.
[64], [65], [75], [76] - Clause 30 of the letter of award and Clause 34.8 work together. The argument that the arbitration agreement in the letter of award displaced Clause 34.8 was raised too late and failed on its merits: the former is the source of jurisdiction and the latter defines the Arbitrator's powers once seized. The Plaintiff had also accepted that power in the arbitration and could not resile from that position. [87]-[89], [97]-[99]
- Revision may go either way. Clause 34.8 does not confine the Arbitrator to revising extension of time upwards. Whether Clause 23.10 impliedly limits that power is a question of construction going to the merits.
It does not, without more, amount to an excess of jurisdiction.
[102]-[105] - No breach of natural justice. The rules protect the parties to the reference, not the architect, a stranger to the award. The Plaintiff knew months in advance that the architect would not be called and chose not to call it.
a party cannot decline to adduce evidence reasonably available to it and then complain, after an adverse award, that the Tribunal ought to have had the benefit of that evidence.
[132]-[136], [143] - No appeal in disguise. The complaints were, at most, errors of law within jurisdiction.
Section 37 AA 2005 does not exist to give a dissatisfied party a second opportunity to relitigate the merits of a technical construction dispute under the guise of a jurisdictional or natural justice challenge.
[146], [147], [151]
What it means for businesses
- Architect's certificates are not final under PAM 2006. Where the contract allows an arbitrator to open up, review and revise certificates, a contractor relying on a favourable extension of time or reassessment should expect the employer to challenge it in the same arbitration, and the result may go either way. [96], [102], [103]
- Positions taken in the arbitration count. Concessions made before the tribunal, such as accepting its power under Clause 34.8, may prevent a party from arguing the opposite in a setting aside application, and new arguments not raised in the arbitration or in the supporting affidavits are unlikely to be entertained. [87], [99], [100]
- Call the witnesses you need. If a certifier's evidence would support a party's case, that party should call the certifier itself rather than rely on the other side to do so. [135], [136], [142]
- Setting aside is a narrow remedy. Section 37 of the Arbitration Act 2005 is not a route to a rehearing of the merits of extension of time and liquidated damages, so parties should present their full case at the arbitration itself. [33], [147], [151]
Numbers in square brackets refer to paragraphs of the grounds of judgment. Passages highlighted are cited directly from the judgment or case report.
Case updates summarise published decisions for general information only. They are not legal advice, and they do not discuss matters in which the firm has acted.